Related documents Search history  | Help
	
	[ clip  ]
	
		
9 document(s) related    
	
		Texas Bills & Amendments: 1    
	
		Misc. items: 8 
	
	
| Texas Bills / Amendments | Caption | Clips | 
|---|---|---|
| 88th Regular Session | ||
| HB 2555 | Relating to transmission and distribution system resiliency planning by and cost recovery for electric utilities. | 8 | 
| 
	 Texas Governor Materials 
	 | 
	Clips  | 
|
|---|---|---|
		
			Governor Abbott demands CenterPoint improve their hurricane preparation, response efforts. (Link Type: Press Release)  | ||
		
			Letter to President and CEO Jason P. Wells, CenterPoint Energy, Inc., RE: Directing CenterPoint Energy, Inc., to provide specified information to the office of the Governor by July 31, 2024 (requesting information about CenterPoint Energy Inc.'s response to Hurricane Beryl). (Link Type: Letter)  | ||
		
			Tex. Gov. Proclamation, Amending a previous proclamation that declared a state of disaster in a certain counties based on the threat posed by Hurricane Beryl on July 5, 2024 and that continues by adding additional counties to the disaster area. (Link Type: Proclamation)  | ||
| 
	 Other 
	 | 
	Clips  | 
|
			
			Filings for 56211 (PUC docket no. 56211); Application of CenterPoint Energy Houston Electric, LLC for authority to change rates (to recover costs of restoring power in Houston following Hurricane Beryl). (Link Type: Agency Document)  | ||
			
			Proposal for decision RE: SOAH Docket No. 473-22-2353; PUC Docket No. 53442; Application of CenterPoint Energy Houston Electric, LLC for approval to amend its distribution cost recovery factor (ruling that state regulators should not let CenterPoint pass its generator costs to consumers). (Link Type: Agency Document)  | ||
			
			Letter to Chairman Peter Lake, et al., Public Utility Commission of Texas, RE: SOAH Docket No. 473-22-2353; PUC Docket No. 53442; Application of CenterPoint Energy Houston Electric, LLC for approval to amend its distribution cost recovery factor (requesting state regulators ignore a prior administrative law judges' decision and approve CenterPoint passing its generator costs to consumers). (Link Type: Letter)  | ||
			
			Letter to Chairman Peter Lake, et al., Public Utility Commission of Texas, RE: SOAH Docket No. 473-22-2353; PUC Docket No. 53442; Application of CenterPoint Energy Houston Electric, LLC for approval to amend its distribution cost recovery factor (requesting state regulators ignore a prior administrative law judges' decision and approve CenterPoint passing its generator costs to consumers). (Link Type: Letter)  | ||
			
			Climate READi: Projected changes in hurricane-induced power outages in a future climate (interactive report including hurricane outage map, power outage prediction model, projected outage events, and more). (Link Type: Website)  | ||